City of Spokane

Spokane Municipal Code

***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17F
Chapter 17F.050
Section 17F.050.100
 

Title 17F Construction Standards

Chapter 17F.050 Electrical Code

Section 17F.050.100 Wiring for Construction Use

A permit and inspection are required for the installation of wiring for construction use, such as to supply power during construction. The inspector may limit the time construction wiring may be used. After inspection and upon approval of the wiring, the inspector notifies the serving utility that connection of the wiring to its distribution system is authorized.

Date Passed: Monday, February 28, 2005

Effective Date: Saturday, April 2, 2005

ORD C33594 Section 4