City of Spokane

Spokane Municipal Code

Home
Title 10
Chapter 10.26
Section 10.26.060
 

Title 10 Regulation of Activities

Division II. License Code

Chapter 10.26 Building Moving and Relocation

Section 10.26.060 Default
  1. If a default in the conditions of the permit is not timely cured, the building official applies the bond to either complete the work required to satisfy the permit conditions or demolish and remove the building, taking into account the standards and criteria contained in chapter 17F.070 SMC.

  2. After paying the costs of the work of completion or demolition, the building official retains twenty-five percent of the costs by way of reimbursement of administrative expense. Any money remaining is returned to the person who paid on the bond.

Date Passed: Monday, January 11, 2016

Effective Date: Wednesday, February 24, 2016

ORD C35344 Section 5

September 27, 2024