City of Spokane

Spokane Municipal Code

***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 13
Chapter 13.03
Section 13.03.0620
 

Title 13 Public Utilities and Services

Chapter 13.03 Sewers

Article VI. Sewer Construction

Section 13.03.0620 Opening Street – Requirements

 

  1. When a sewer is constructed requiring the opening of the street, the paving and earth must be deposited in a manner that will cause the least inconvenience to the public and provide for free drainage along the gutter.
    1. One-half of the street must be kept clear for the passage of vehicles and bridgeways must be provided on sidewalks for foot passengers.
    1. In refilling the pipe zone and trench, refer to Design Standard A-1 as prescribed in regulations, or as required by the Wastewater Superintendent, to prevent settlement.
  1. As soon as any such drain or sewer is completed, the paving, curbing and sidewalk must be restored to a condition equal to or exceeding that existing previous to the excavation and all rubbish and surplus earth must be immediately removed.
  1. On arterial streets and avenues, traffic is to be routed and controlled and construction performed as may be directed by the Director of the Development Services Center  or the Street Director.

 

Date Passed: Monday, December 8, 2025

Effective Date: Sunday, January 18, 2026

ORD C36776 Section 40