Title 13 Public Utilities and Services
Chapter 13.08 Utility Cost Recovery Methods
Article II. Special Connection Charges (formerly 13.03.0702 to 13.03.0712)
Section 13.08.210 Special Connection Charge Authorized - Basis
- In addition to connection, permit, tap and meter fees required by this code, there is imposed, upon the owners of properties which have not been assessed or charged or contributed the property’s pro-rata share of the cost of construction of the City’s sewerage or water system, must pay prior to connection to a City utility, a special connection charge in an amount to be computed under SMC 13.08.250.
- Property owners subject to the special connection charge must execute and record all appropriate documents required by this chapter necessary to secure full payment and costs of collection, including reasonable attorney’s fees.
- Projects subject to the special connection charge are specifically identified by the City and are subject to the express review and approval of the city council.
Date Passed: Monday, March 31, 2025
Effective Date: Saturday, May 10, 2025
ORD C36654 Section 12