Title 17G Administration and Procedures
Chapter 17G.040 Design Review Board Administration and Procedures
Section 17G.040.090 Vesting
Vesting for Project Permits.
A complete application for a project permit that is entitled to vesting under Washington law and that is subject to design review shall be considered under the land use codes and other land use control ordinances in effect on the date a complete application for either a design review collaborative workshop or an administrative design review process as set forth in chapter 17G.040 SMC is submitted to the director, provided that a complete project permit application is filed within one hundred eighty days of the design review board final recommendation.
Date Passed: Monday, December 14, 2009
Effective Date: Saturday, January 16, 2010
Ordinance C34526 Section 1