Within fourteen days of the issuance of a determination of a complete application, a notice of application shall be provided for Type I, II and III project permit applications in accordance with this section (RCW 36.70B.110.2). The notice of application shall follow the public notice requirements contained in SMC 17G.060.110 through 17G.060.120. The notice of application may be combined with the notice of public hearing, if a hearing has been scheduled by notice of application. The date, time, place and type of hearing, SEPA determination and SEPA appeal deadline (using the optional DNS process) are required to be added to the notice of application if this provision is used (RCW 36.70B.110(2)(f)).

Date Passed: Monday, February 21, 2005

Effective Date: Wednesday, March 30, 2005

ORD C33578 Section 4