Title 17G Administration and Procedures

Chapter 17G.060 Land Use Application Procedures

Section 17G.060.130 Public Comment Period
  1. The public comment period for Type I, II, and III applications is fifteen days, except short subdivision applications with minor engineering review as provided in SMC 17G.080.040(C)(2) shall have no public comment period.
  1. The public comment period for a shoreline substantial development permit, shoreline conditional use, or shoreline variance shall be thirty days.
  1. The public comment period for a shoreline substantial development permit for limited utility extensions and bulkheads shall be twenty days (WAC 173-27-120).
  1. The longest public comment period shall prevail.

Date Passed: Monday, June 27, 2022

Effective Date: Sunday, August 7, 2022

ORD C36224 Section 3