City of Spokane

Spokane Municipal Code

Home
Title 17G
Chapter 17G.060
Section 17G.060.130
 

Title 17G Administration and Procedures

Chapter 17G.060 Land Use Application Procedures

Section 17G.060.130 Public Comment Period

  1. The public comment period for Type I, II, and III applications is fifteen days.
     
  2. The public comment period for a shoreline substantial development permit, shoreline conditional use, or shoreline variance shall be thirty days.
     
  3. The public comment period for a shoreline substantial development permit for limited utility extensions and bulkheads shall be twenty days (WAC 173-27-120).
     
  4. The longest public comment period shall prevail.

Date Passed: Monday, November 3, 2008

Effective Date: Monday, July 26, 2010

ORD C34327 Section 5