Title 08 Taxation and Revenue
Chapter 08.02 Fees and Charges
Article III. Building and Construction Permits
Section 08.02.035 Mechanical Code
- Mechanical inspection fees are provided in the Development Fee Schedule.
- Reinspection fees for work that was not ready, for corrections previously identified, or for an inaccessible site are provided in the Development Fee Schedule.
- Where work has commenced without first obtaining the required permit(s) or where work was performed by a person without a heating mechanics license pursuant to SMC 10.29.030, an unauthorized work fee shall be imposed in the amount in the Development Fee Schedule. The unauthorized work investigation fee may be assessed against the person performing the work without a license or against the employer or contractor directing the work who failed to obtain the required permit.
- Processing fees are provided in the Development Fee Schedule.
Date Passed: Monday, December 9, 2024
Effective Date: Wednesday, January 22, 2025
ORD C36619 Section 8