City of Spokane

Spokane Municipal Code

***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 13
Chapter 13.03A
Section 13.03A.0404
 

Title 13 Public Utilities and Services

Chapter 13.03A Pretreatment

Article IV. Reporting Requirements

Section 13.03A.0404 Compliance Schedules to Meet Applicable Pretreatment Requirements [4.4]
  1. Whenever a compliance schedule is set up under this chapter, it must include increments of progress or milestones with dates for accomplishment of each milestone. The milestones are major events leading to construction and operation of pretreatment required for the user to meet applicable pretreatment standards (e.g. hiring an engineer, completing preliminary plans, final plans, signing contracts, commencing construction, completing construction, by way of examples).
  1. No milestone time increment in subsection (A) of this section shall exceed nine months.
  1. Not later than fourteen days following each milestone date, and the final date for compliance, the user must submit a progress report to the Plant Manager specifying whether it has complied with the schedule and if not, when it expects to comply, reasons for delay and steps taken to avoid further delays. Not more than nine months shall elapse between milestone reports. All submittals under this section must be signed as provided in SMC 13.03A.0305(A) Fees will be assessed in accordance with SMC 13.03A.1401.

NOTE: Bracketed enumerations reference the numbering in the EPA Region 10 Model Ordinance of March 27, 2012.

Date Passed: Monday, November 9, 2020

Effective Date: Wednesday, December 16, 2020

ORD C35961 Section 41