***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 13
Chapter 13.03A
Section 13.03A.0405
 

Title 13 Public Utilities and Services

Chapter 13.03A Pretreatment

Article IV. Reporting Requirements

Section 13.03A.0405 Notification of Significant Production Changes [4.5]
  1. Any user operating under a discharge permit incorporating equivalent mass or concentration limits shall notify the Plant Manager in writing within two business days after the user knows or has a reasonable basis to know that production levels will significantly change in the ensuing calendar month and request approval. A user failing to give such notice and obtain approval in writing is required to comply with existing limits in the permit. A significant production level change is one as has been specified by the Plant Manager as significant, or in absence of this, a change of twenty percent or greater. All submittals under this section must be signed as provided in SMC 13.03A.0305(A) and accompanied by a review fee as provided in SMC 13.03A.1401.
  1. Additionally, the user must submit a permit modification application as provided in SMC 13.03A.0310, which must include an engineering report detailing the features of the change, including pertinent data and analysis.

NOTE: Bracketed enumerations reference the numbering in the EPA Region 10 Model Ordinance of March 27, 2012.

Date Passed: Monday, November 9, 2020

Effective Date: Wednesday, December 16, 2020

ORD C35961 Section 42