***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17C
Chapter 17C.356
Section 17C.356.030
 

Title 17C Land Use Standards

Chapter 17C.356 Eligible Facilities Modifications

Section 17C.356.030 Application Review
  1. Application. The department shall prepare and make publicly available an application form which shall be limited to the information necessary for the department to consider whether an application is an Eligible Facilities Request. The application may not require the applicant to demonstrate a need or business case for the proposed modification.

  2. Type of Review. Upon receipt of an application for an Eligible Facilities Request pursuant to this Chapter, the department shall review such application to determine whether the application so qualifies.

  3. Timeframe for Review. Within 60 days of the date on which an applicant submits an application seeking approval under this Chapter, the department shall approve the application unless it determines that the application is not covered by this Chapter.

  4. Tolling of the Timeframe for Review. The 60-day review period begins to run when the application is filed, and may be tolled only by mutual agreement by the department and the applicant, or in cases where the department determines that the application is incomplete. The timeframe for review is not tolled by a moratorium on the review of applications.

    1. To toll the timeframe for incompleteness, the department must provide written notice to the applicant within 30 days of receipt of the application, specifically delineating all missing documents or information required in the application.

    2. The timeframe for review begins running again when the applicant makes a supplemental submission in response to the department’s notice of incompleteness.

    3. Following a supplemental submission, the department will notify the applicant within 10 days that the supplemental submission did not provide the information identified in the original notice delineating missing information. The timeframe is tolled in the case of second or subsequent notices pursuant to the procedures identified in paragraph (d) of this section. Second or subsequent notices of incompleteness may not specify missing documents or information that were not delineated in the original notice of incompleteness.

  5. Interaction with Section 332(c)(7). If the department determines that the applicant’s request is not covered by Section 6409(a) as delineated under this Chapter, the presumptively reasonable timeframe under Section 332(c)(7), as prescribed by the FCC’s Shot Clock order, will begin to run from the issuance of the department’s decision that the application is not a covered request. To the extent such information is necessary, the department may request additional information from the applicant to evaluate the application under Section 332(c)(7), pursuant to the limitations applicable to other Section 332(c)(7) reviews.
  6. Failure to Act. In the event the department fails to approve or deny a request seeking approval under this Chapter within the timeframe for review (accounting for any tolling), the request shall be deemed granted. The deemed grant does not become effective until the applicant notifies the applicable reviewing authority in writing after the review period has expired (accounting for any tolling) that the application has been deemed granted.

Date Passed: Monday, November 2, 2015

Effective Date: Monday, November 2, 2015

ORD C35313 Section 1