Title 17D City-wide Standards
Chapter 17D.100 Historic Preservation
Section 17D.100.215 Vesting Project Permits
A complete application for a project permit that is entitled to vesting under Washington law and that is subject to a certificate of appropriateness shall be considered under the land use codes and other land use control ordinances in effect on the date a complete application for a certificate of appropriateness as set forth in chapter 17D.100 SMC is submitted to the HPO, provided that a complete project permit application is filed within one hundred eighty days of the landmark commission’s final decision.
Date Passed: Monday, September 16, 2019
Effective Date: Friday, November 1, 2019
ORD C35807 Section 7