Section 17G.010.130 Application Submission Requirements – Ministerial Permits Exempt from SEPA
Each permit application subject to this chapter includes a general application providing the information specified by the permitting department. Each application also includes one or more supplemental applications for the specific permit(s) requested and provides the information described in SMC 17G.010.140 through 17G.010.230. A permit application is not considered complete and is not reviewed or heard until such information and material as required by these sections is submitted and all required fees are paid. If an application is determined to be incomplete, the applicant is notified in writing within seven days. The notice identifies the missing material or information necessary to complete the application.
Date Passed: Monday, February 21, 2005
Effective Date: Wednesday, March 30, 2005
ORD C33578 Section 1