***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 17G
Chapter 17G.061
Section 17G.061.350
 

Title 17G Administration and Procedures

Chapter 17G.061 Land Use Application Procedures

Section 17G.061.350 Expiration of Permit
  1. Table 17G.061.010-1 indicates the expiration provisions for land use permits within the City of Spokane. 
  1. The term for a permit shall commence on the date of the hearing examiner or director’s decision, provided that in the event the decision is appealed, the effective date shall be the date of decision on appeal. The term for a shoreline permit shall commence on the effective date of the permit as defined in WAC 173-27-090. 
  1. A permit under this chapter shall expire if, on the date the permit expires, the project sponsor has not submitted a complete application for building permit or the building permit has expired. 
  1. In accordance with WAC 173-27-090, the director may authorize a single extension before the end of the time limit for up to one year if a request for extension has been filed before the expiration date and notice of the proposed extension is given to the parties of record and to the department of ecology. The extension must be based on reasonable factors. Extensions of time for plats, short plats and binding site plan are subject to the extension provisions of SMC 17G.080.020(M)

Date Passed: Monday, November 20, 2023

Effective Date: Monday, January 1, 2024

ORD C36459 Section 35