***Note: Many local criminal codes can now be located under Chapter 10.60 SMC while others are now cited under the Revised Code of Washington (RCW), which was incorporated into the municipal code in 2022. (See SMC 10.58.010). Code Enforcement, including Noise Control and Animal Regulations are located in Chapters 10.62 through 10.74.

Home
Title 07
Chapter 07.06
Section 07.06.167
 

Title 07 Finance

Chapter 07.06 Procurement of Goods, Services and Works

Article II. Public Bidding and Other Provisions

Section 07.06.167 Limited Public Works Process
  1. If a work, construction, alteration, repair, or improvement project is estimated to cost less than $35,000 for Limited Public Works Projects, the City may award such a contract using the limited public works process provided under RCW 39.04.155(3).  For a limited public works project, the City will solicit electronic or written quotations from a minimum of three (3) contractors from the appropriate SWR and shall award the contract to the lowest responsible bidder as defined under RCW 39.04.010. After an award is made, the quotations shall be open to public inspection and available by electronic request.

  2. For limited public works projects, the City may waive the payment and performance bond requirements of chapter 39.08 RCW and the retainage requirements of chapter 60.28 RCW, thereby assuming the liability for the contractor’s nonpayment of laborers, mechanics, subcontractors, material persons, suppliers, and taxes imposed under Title 82 RCW that may be due from the contractor for the limited public works project. However, the City shall have the right of recovery against the contractor for any payments made on the contractor’s behalf.

  3. The City shall maintain a list of the contractors contacted and the contracts awarded during the previous twenty four (24) months under the limited public works process, including the name of the contractor, the contractor's registration number, the amount of the contract, a brief description of the type of work performed, and the date the contract was awarded.

Date Passed: Monday, March 12, 2018

Effective Date: Saturday, April 21, 2018

ORD C35602 Section 2