2019 (Cycle 9) Traffic Calming – Various Locations Citywide

Project Number: 2019088

Status: Construction

Construction Estimate: $1,000,000

Project Description: Miscellaneous street and sidewalk improvements focused on pedestrians and traffic calming. This project is funded with local funds.

Project Location(s) and Schedule

District 2

  • Lincoln Heights: Marked crosswalk on Southeast Boulevard at Lincoln Park driveway.
  • Manito/Cannon Hill: Bumpout on the northwest corner of Bernard at 21st Avenue.

District 3

  • Balboa/South Indian Trail: Bike signage on Woodside Avenue between Indian Trail and Five Mile Road.
  • North Hill: Marked crosswalk with bumpouts at Garland/Madison.
  • North Indian Trail: Marked crosswalk with bumpouts at Barnes/Farmdale on the west leg of the intersection. Bumpouts on both sides of Barnes. Include signage, illumination, ADA ramps, and revisions to stormwater facilities as needed.
  • North Indian Trail: Indian Trail/Lowell install a Pedestrian Hybrid Beacon for the crosswalk on the north leg.
  • West Central: Add crosswalk signage and advance warning signs at Broadway/Chestnut at Dutch Jake's Park.

Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: No
  • Planned Lane Restrictions: Yes - as needed
  • Planned Road Closures: No
  • Planned Utility Work: Yes - minor storm and sewer repairs
  • Pavement Cut Moratorium In Effect: No

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Construction Start Date: September 15, 2022

Expected Construction Completed Date: September 19, 2022

Contract Award Date: June 27, 2022

Contractor: Bacon Concrete, Inc.

City Project Manager - Construction Phase: Kelly Heitstuman, 509.625.7759, kheitstuman@spokanecity.org

City Project Manager - Design Phase: David St. Pierre, 509.625.6700, dstpierre@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
To be determined

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or engineeringadmin@spokanecity.org.