2021 Residential Grind and Overlay South

Project Number: 2021066

Status: Complete

Construction Estimate: $1,000,000

Project Description: Repave residential streets. Minor storm sewer system repairs and upgrades may also be completed as part of the paving project.

Project Location(s) and Schedule*

  • Manito Boulevard from 22nd Avenue to Manito Place: September 13 – October 7
  • Manito Boulevard from 33rd Avenue to 29th Avenue: September 13 – October 7
  • 31st Avenue from Division Street to Bernard Street: September 13 – October 7
  • Howard Street from 5th Avenue to 7th Avenue: October 8 - November 12
  • 6th Avenue from Washington Street to Wall Street: October 8 - November 12
  • 26th Avenue from Tekoa Street to Bernard Street: October 8 - November 12

*Crews will be in the area during this time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Contractors are responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business days' notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: No
  • Planned Lane Restrictions: Yes: As needed
  • Planned Road Closures: Yes: All locations will have road closures—only local traffic will be allowed through
  • Planned Utility Work: Yes: Storm water upgrades
  • Pavement Cut Policy In Effect: Yes

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily restrict traffic. For everyone's safety, please obey all traffic signs.

Construction Start Date: September 13, 2021

Construction Completed Date: November 12, 2021

Contract Award Date: August 16, 2021

Contractor: Shamrock Paving, Inc.

City Project Manager - Construction Phase: Mike Zangara, 509.625-7722, mzangara@spokanecity.org

City Project Manager - Design Phase: Rich Proszek, 509.625.6700, rproszek@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor’s public representative:

Talia Brestar
509.638.3443
talia.b@shamrockpaving.us

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or engineeringadmin@spokanecity.org.

Related Links