2021 Street Maintenance Curb Ramps (Various Locations Citywide)

Project Number: 2021042

Status: Completed

Construction Estimate: $690,270

Project Description: This project consists of installing curb ramps on streets where the Street Department has or will be doing grind and overlay work. This project is funded with local funds.

Project Location(s) and Schedule

District 1:

  • S. Helena St. – E. Sprague Ave. to E. 2nd Ave.: April 6 – April 11
  • N. Perry St. – E. Wellesley Ave. to E. Empire Ave.: April 6 – April 11
  • N. Perry St./N. Center St. and E. Montgomery Ave.: April 2 – April 6
  • N. Perry St. – E. Carlisle Ave. to E. Buckeye Ave.: April 2 – April 6
  • E. Empire Ave – N. Morton St. to N. Helena St.: April 6 – April 11
  • E. Central Ave and N. Ruby St.: April 6 – April 11

District 2:

  • W. 14th Ave. – S. Adams St. to S. Monroe St.: May 9 – May 18
  • W. 4th Ave. and S. Bernard St.: May 9 – May 18
  • W. 4th Ave  and S. McClellan St.: May 9 – May 18
  • S. Browne St. and W. 5th Ave.: May 9 – May 18
  • S. Browne St. and W. 6th Ave.: May 9 – May 18
  • 7th Ave and McClellan St.: May 9 – May 18

District 3:

  • N. Post St. – W. Fairview Ave. to W. Walton Ave.: April 11 – April 26
  • W. Garland Ave. – N. Walnut St. to N. Madison St.: April 25 – May 4 
  • W. Boone Ave. and N. Nettleton St.: May 4 – May 9
  • W. Boone Ave. and N. Oak St.: May 4 – May 9
  • North River drive between Division and Washington: May 4 – May 9

Schedule to be determined. Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: No
  • Planned Lane Restrictions: Yes - as needed throughout the project
  • Planned Road Closures: No
  • Planned Utility Work: Yes - stormwater facilities as needed
  • Pavement Cut Moratorium In Effect: No

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: April 2, 2022

Expected Construction Completed Date: Summer 2022

Contract Award Date: November 22, 2021

Contractor: Cameron-Reilly, LLC

City Project Manager - Construction Phase: Kelly Heitstuman, 509.625.7759, kheitstuman@spokanecity.org

City Project Manager - Design Phase: Rich Proszek, 509.625.6700, rproszek@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative: