Cochran Basin Disc Golf and Boat Launch Stormwater Treatment Facility

Project Number: 2018058

Status: Design

Construction Estimate: $2,500,000

Project Description: Construction of treatment and infiltration ponds at the Downriver Disc Golf Course (west of Downriver Golf Course) to treat stormwater generated in the Cochran Basin which includes most of north Spokane. This project is funded with state and local funds.

Project Location(s) and Schedule

  • West of Downriver Golf Course to northwest of TJ Meenach Bridge

Schedules to be determined.

Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: To be determined
  • Planned Lane Restrictions: To be determined
  • Planned Road Closures: Access to the boat launch area will be closed for the duration of the project.
  • Planned Utility Work: To be determined
  • Pavement Cut Moratorium In Effect: No

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: July 2022

Expected Construction Completed Date: May 2023

Contract Award Date: Expected to be bid in May of 2022

Contractor: To be determined

City Project Manager - Construction Phase: To be determined

City Project Manager - Design Phase: Jonathan Adams, 509.625.6700, jradams@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
To be determined