Project Number: 2019148
Status: Construction
Construction Estimate: $7,307,265
Project Description: This project will construct stormwater flow control vault.
Project Location(s) and Schedule
Southeast corner of intersection TJ Meenach Drive and Northwest Boulevard
Schedules to be determined.
Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.
Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.
Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.
Construction Zone Details
Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.
Construction Start Date: June 5, 2023
Expected Construction Completed Date: 2024
Contract Award Date: February 15, 2023
Contractor: DW Excavating
City Project Manager - Construction Phase: John Hogberg, jhogberg@spokanecity.org, 509.625.7755
City Project Manager - Design Phase: Jonathan Adams, jadams@spokanecity.org, 509.625.6700
For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
Cortney Wilson
Cortney@dwexcavating.net
If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or engineeringadmin@spokanecity.org.