Garbage and curbside recycling pickup will be a day late starting Wednesday, with Friday's pickup occurring on Saturday due to the Christmas holiday. Please have your carts out at the point of collection by 6 AM on your collection day. See more information regarding other City closures.

CSO Basin 25 and Peaceful Valley Trail Shoreline Conditional Use Permit

Application/Permit Number: Z17-256CUP3

Location

The work spans from Glover Field (35183.2101) to People's Park (25242.1201) in Peaceful Valley. There are dozens of city parcels involved in the project, as well as work in the adjacent right-of-way. Please refer to the site plan submitted with the application for a complete picture of the location.

Applicant

City of Spokane, Engineering Services

Description

The City of Spokane proposes a two-year phased project to construct new and replace water/sewer stormwater mains and swales, as well as the Peaceful Valley Trail. Phase 1 will consist of construction of the CSO basin and utility replacement and installation adjacent to Glover Field along Main Ave to Cedar St. Phase 2 will consist of the construction of the mixed-use trail, adjacent street rebuilds and utility installation along the remainder of the project.

Decision

A public hearing was held on this proposal on Thursday June 8th, 2016 at 9:30AM. The decision was issued on June 22nd, 2017 by the Hearing Examiner. The date of the last day to appeal is July 5th, 2017 at 5:00PM

Related Documents


Contact Information

Written comments should be sent via mail or email:

Planning and Development Services
Ali Brast
Assistant Planner
808 W. Spokane Falls Blvd.
Spokane, WA 99201-3329
abrast@spokanecity.org