Cure-In-Place Pipe (CIPP) 2020 Sanitary Sewer Rehabilitation

Project Number: 2021078

Status: Construction

Construction Estimate: $1,354,009

Project Description: Install cure-in-place pipe

Project Location(s) and Schedule
Various locations citywide

Schedules to be determined.

Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: No
  • Planned Lane Restrictions: Yes
  • Planned Road Closures: No
  • Planned Utility Work: Yes
  • Pavement Cut Moratorium In Effect: No

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: February 2023

Expected Construction Completed Date: March 2023

Contract Award Date: April 11, 2022

Contractor: Iron Horse, LLC

City Project Manager - Construction Phase: Mike Zangara, 509.625.7766, mzangara@spokanecity.org

City Project Manager - Design Phase: Dan Buller, 509-525-6800, dbuller@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
To be determined

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or engineeringadmin@spokanecity.org.

Related Links