Project Number: 2020061
Construction Estimate: $750,000
Project Location: Upriver Hydroelectric Dam
Description: Replacement of well pump and motor located at the Upriver Hydroelectric & Waterworks Facility. This project will be funded with local funds.
Status: Design
Contractor: General Industries, Inc.
Project Manager - Design: Dan Buller, 509.625.6700, dbuller@spokanecity.org
Project Manager - Construction: Construction Management, 509.625.7722
Construction Start Date: Spring 2021
Substantially Completed Date: Fall 2021
Award Date: January 4, 2021
In order to preserve pavement life, the City of Spokane's Pavement Cut Policy is in effect for all street-related projects.