Wellesley – Freya to Havana Reconstruction Project

Project Number: 2018076

Status: Construction

Project Description: Full reconstruction of Wellesley from Freya to Havana (35-ft., 3-lanes), including stormwater improvements, street trees, and replacing water distribution main, and sidewalk on the north side of the street and shared use path on the south side.

Documents

Project Schedule

  • Initial Public Outreach to Property Owners Impacted: Summer/Fall 2023
  • Finalize Project Scope: Fall 2023
  • Design Phase: Fall 2023 – Early 2024
  • Right of Way Acquisition: 2024
  • Advertise for Bids: Late 2024

Construction Start Date: March 30, 2026

Construction Completion Date: Early August 2026

Contractor: Inland Infrastructer

Construction Estimate: $4,500,000
Funding sources have been secured and include $3.62 million in federal grants, Northeast PDA, and the City of Spokane Water Department.


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor’s public representative:

Contractor Public Liaison
Jordan Klinke, 509.514.0639

If the contractor’s public representative cannot resolve your issue, please contact the City of Spokane – Engineering Services at 509.625.6700 or engineeringadmin@spokanecity.org.

City Construction Relations Manager
Annie Deasy, 509.625.6102

City Project Manager – Design Phase
Kristy Warren

City Project Manager – Construction Phase
John Hogberg