The City of Spokane, by law is required to collect certain information on PW projects regardless of dollar amount. For this reason all PW contractors are required to:
In Addition to the above:
| Retainage Release on Contracts < 35K |
Retainage Release on Contracts > 35K |
|---|---|
- Verification of no claims and liens against retainage and bonds. - And minimum 45 days after date on Final Acceptance Letter. |
- Release after approval of Notice of Completion filed with LNI, DOR and ESD; - And verification of no claims and liens against retainage and bonds; - And minimum of 45 days after date on Final Acceptance Letter |
After bid due date and time and prior to award, the apparent low bidder shall complete, sign, and submit the following form(s). The form shall be submitted within twenty-four (24) hours after notification by the bid coordinator unless a different time and date is required by the specifications or otherwise mutually agreed upon.
Alternate Filing Options
Additional Information