Chestnut St. Bridge Scour Mitigation

Project Number: 2022093

Status: Construction

Project Timeline

Construction Start Date: July 2026

Construction Completion Date: October 2026

Project Description

This project will include scour damage repair of the Chestnut St. Bridge including stream bottom and bank restoration, removal of fill, improve hydraulics under the bridge, rip/rap and repair around piers. No work is being done on the bridge structure or deck.

Key Objectives

  • Hydraulic/Scour Analysis: Evaluate channel conditions and address erosion risks.
  • Structural Repairs: Place riprap around piers and abutments.
  • Stream Restoration: Remove fill material and stabilize streambed and banks.

Construction Estimate: $2,037,000 million


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor’s public representative.

Contractor Public Representative
Peter Nelson, 509.928.3333

City Construction Relations Manager
Annie Deasy, 509.625.6102

City Project Manager – Design Phase
Dan Buller

Project Manager – Construction Phase
Jeff Sorenson, PE Keller Associates