Havana Well Pump Station

Project Number: 2019171

Status: Complete

Construction Estimate: $5,711,636

Project Description: Construct two building well pump station for six new wells (already drilled) including pumps, motors, controls, and yard piping. Project is funded with local funds.

Project Location(s) and Schedule

  • Havana Street and 6th Avenue

Project is scheduled to start in early spring and will take 12 to 14 months to complete. Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Construction will cause increased noise and dust. The contractor is required to control dust. The construction site will be fully fenced.

Avista will be burying an overhead power line that is located on the site. Limited service interruptions of a few hours will occur. Homeowners will receive advanced notice prior to any interruption.

Water service will be maintained throughout construction. Limited service interruptions of a few hours will occur. Homeowners will receive advanced notice prior to any interruption.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Exterior construction work should be mostly complete by fall of 2022. The majority of the remainder of the work will be completed inside the buildings.

Construction Zone Details

  • Planned Detours: Yes – to be determined
  • Planned Lane Restrictions: No
  • Planned Road Closures: Yes – temporary three-week closure expected on Havana
  • Planned Utility Work: Yes – installation of communications tower; Avista work
  • Pavement Cut Moratorium In Effect: Yes

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Construction Start Date: June 1, 2022

Construction Completed Date: June 26, 2024

Contract Award Date: Dec. 13, 2021

Contractor: LaRiviere, Inc.

City Project Manager - Design Phase: Dan Buller, dbuller@spokanecity.org, 509.625.6700

City Project Manager - Construction Phase: Amanda Anderson, amanderson@spokanecity.org, 509.625.7781