Havana Well Pump Station

Project Number: 2019171

Construction Estimate: $4,000,000

Project Location: Havana & 5th Ave

Description: Construct two building well pump station for six new wells (already drilled) including pumps, motors, controls, and yard piping. Project is funded with local funds.

Status: Design

Contractor: To be determined

Project Manager - Design: Rich Proszek, 509.625.6700, rproszek@spokanecity.org

Project Manager - Construction: Construction Management, 509.625.7722

Construction Start Date: Spring 2020

Substantially Completed Date: Spring 2021

Award Date: To be determined