Holland Avenue Sewer (Normandie to Colton)

Project Number: 2021082

Status: Design

Construction Estimate: $4,500,000

Project Description: This project will construct a gravity sewer pipe from North Pointe Lift Station (Colton and Holland) to the intersection of Holland and Normandie where the pipe will connect to Spokane County's conveyance system. This new pipe will allow the City to take the North Pointe Lift Station out of service and eliminate the problematic force main associated with the lift station.

Project Location(s) and Schedule

  • Normandie Lane to Colton Street. Schedule to be determined.

Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: Yes – to be determined
  • Planned Lane Restrictions: Yes – as needed
  • Planned Road Closures: Yes – as needed
  • Planned Utility Work: Yes - sanitary sewer pipe; work may be needed to accommodate Century Link.
  • Pavement Cut Moratorium In Effect: Yes - curb-to-curb pavement reconstruction along entire pipe realignment.

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: 2023

Expected Construction Completed Date: 2023

Contract Award Date: Expected to go to bid in 2023

Contractor: To be determined

City Project Manager - Construction Phase:To be determined

City Project Manager - Design Phase: David St. Pierre, 509.625.6700, dstpierre@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
To be determined

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or eraea@spokanecity.org.

Related Links