Project Number: 2018097
Status: Complete
Construction Estimate: $2,529,036
Project Description: Construct a shared-use pathway under the Monroe Street Bridge connecting Main Avenue west of Monroe Street to the existing path attached to the north side of Spokane Falls Boulevard across from the Central Library.
Construction Start Date: Sept. 11, 2023
Construction Completed Date: June 14, 2024
Contract Award Date: July 10, 2023
Contractor: Halme Construction
City Project Manager - Design Phase: Mark Serbousek, mmserbousek@spokanecity.org, 509.625.6154
City Project Manager - Construction Phase: Construction Management