Project Number: 2018097

Status: Complete

Construction Estimate: $2,529,036

Project Description: Construct a shared-use pathway under the Monroe Street Bridge connecting Main Avenue west of Monroe Street to the existing path attached to the north side of Spokane Falls Boulevard across from the Central Library.

Construction Start Date: Sept. 11, 2023

Construction Completed Date: June 14, 2024

Contract Award Date: July 10, 2023

Contractor: Halme Construction

City Project Manager - Design Phase: Mark Serbousek, mmserbousek@spokanecity.org, 509.625.6154

City Project Manager - Construction Phase: Construction Management