Spokane International Airport Reservoir

Project Number: 2018050

Status: Construction

Construction Estimate: $13,270,000

Project Description:Construct a new 3.6 MG elevated composite water tank. Project is funded with local and state funds.

Project Location(s) and Schedule

  • Spokane International Airport

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: Spring 2022

Expected Construction Completed Date: Fall 2024

Contract Award Date: Award still being determined

Contractor: To be determined

City Project Manager - Construction Phase: Construction Management, 509.625.7722, rschulte@spokanecity.org

City Project Manager - Design Phase: Rich Proszek, 509.625.6700, rproszek@spokanecity.org


Contact Information

Karin Janssen
509.625.6102
kjanssen@spokanecity.org