Garbage, recycling, and yard waste services will be a day late all week, with Friday's pickup occurring on Saturday due to the Memorial Day holiday. Please have your carts out at the point of collection by 6 AM on your collection day. For more information on city-wide closures, please refer to our news release.

Spokane International Airport Reservoir

Project Number: 2018050

Status: Completed

Construction Estimate: $13,270,000

Project Description:Construct a new 3.6 MG elevated composite water tank. Project is funded with local and state funds.

Project Location(s) and Schedule

  • Spokane International Airport

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Construction Start Date: May 22, 2023

Expected Construction Completed Date: November 2024

Contract Award Date: November 17, 2021

Contractor: Landmark Structures

City Project Manager - Construction Phase: Amanda Anderson, aanderson@spokanecity.org

City Project Manager - Design Phase: Rich Proszek, 509.625.6700, rproszek@spokanecity.org


Contact Information

City of Spokane - Engineering Services
509.625.6700
eraea@spokanecity.org