Spokane International Airport Reservoir

Project Number: 2018050

Status: Construction

Construction Estimate: $13,270,000

Project Description:Construct a new 3.6 MG elevated composite water tank. Project is funded with local and state funds.

Project Location(s) and Schedule

  • Spokane International Airport

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Construction Start Date: April 2022

Expected Construction Completed Date: 2024

Contract Award Date: November 17, 2021

Contractor: To be determined

City Project Manager - Construction Phase: OAC/Tim Kyker, 509.625.7756, tkyker@spokanecity.org

City Project Manager - Design Phase: Rich Proszek, 509.625.6700, rproszek@spokanecity.org


Contact Information

City of Spokane - Engineering Services
509.625.6700
eraea@spokanecity.org