Please note: if you are searching for the new 2023 Thor-Freya project, please visit our new project page.

Thor-Freya Reconstruction (Hartson to Sprague)

Project Number: 2019135

Status: Construction

Construction Estimate: $8,959,665

Project Description: Full roadway reconstruction, curb and stormwater facilities replacement, ADA ramp upgrades, and water/sewer replacements. This project is funded with federal and local funding.

Project Location(s) and Schedule

  • Thor Street and Freya Street from Hartson Avenue to Sprague Avenue
  • Hartson Avenue from Thor to Freya

Construction Schedule

Construction will be conducted in seven phases as follows:

  • Phases 1-3: End of March through late July 2022
  • Phases 4-5: Mid-July through late August/early September 2022
  • Phases 6-7: Late August through early-mid October 2022

Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays. Please check back often to ensure you have the most current information.

If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: Yes – Thor-Freya Construction Phasing (PDF 813 KB)
  • Planned Lane Restrictions: Yes – as needed throughout the project
  • Planned Road Closures: Yes – full closures will occur for roadway in each construction phase
  • Planned Utility Work: Yes – storm water; sanitary sewer; water mains; communication conduit
  • Pavement Cut Moratorium In Effect: Yes

Construction Phasing
Construction will be broken out into seven phases to ensure access is maintained to all businesses throughout the project. Work may occur on two phases at a time. When work occurs on Thor, Freya will have two-way traffic. When work occurs on Freya, Thor will have two-way traffic. During each phase, the section of road being worked on will be fully closed to all traffic. Once a phase is complete, that section of road will be opened to traffic.

Road work will take longer to complete on this project as the roadway will be concrete as opposed to asphalt. Work will produce noise and dust, but no extensive rock hammering is needed. The contractor must adhere to City noise ordinances—work must be completed between 7:00 a.m. and 10:00 p.m. The contractor is required to provide dust control.

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: March 2022

Expected Construction Completed Date: May 2023

Contract Award Date: October 25, 2021

Contractor: Cameron-Reilly, LLC

City Project Manager - Construction Phase: Ryan Coles, 509.625.7718, rcoles@spokanecity.org

City Project Manager - Design Phase: Dan Buller, 509.625.6700, dbuller@spokanecity.org


Construction Updates

If you would like to sign up for weekly project updates, please email Tina Westby at tina@cameron-reilly.com.

Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
Tina Westby
Cameron-Reilly, LLC
509.867.4398
tina@cameron-reilly.com

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or engineeringadmin@spokanecity.org.

Related Links