TJ Meenach Street, Siphon, and Stormwater Improvements

Project Number: 2014153

Status: Completed

Construction Estimate: $3,575,095

Project Description: This project will design and construct stormwater and sanitary sewer improvements in coordination with the TJ Meenach Drive street reconstruction project.

Project Location(s)
North TJ Meenach Drive from TJ Meenach Bridge to Northwest Boulevard, including Downriver Boat Launch area

Construction Start Date: March 2023

Expected Construction Completed Date: October 2023

Contract Award Date: January 2023

Contractor: Halme Construction

City Project Manager - Construction Phase: John Hogberg, 509.625.7722, jhogberg@spokanecity.org

City Project Manager - Design Phase: Jonathan Adams, 509.625.6700, jradams@spokanecity.org