TJ Meenach Street, Siphon, and Stormwater Improvements

Project Number: 2014153

Status: Design

Construction Estimate: $7,000,000

Project Description: This project has been pushed to the 2023 construction season due to ongoing procurement issues. . This project will design and construct stormwater and sanitary sewer improvements in coordination with the TJ Meenach Drive street reconstruction project.

Project Location(s) and Schedule
North TJ Meenach Drive from TJ Meenach Bridge to Northwest Boulevard, including Downriver Boat Launch area

Schedules to be determined.

Crews will be in the area during the scheduled time frame. All schedules are approximate and dependent on weather and unforeseen delays.

Once the contract has been awarded, contractors will be responsible for setting and maintaining the schedule for the work to be done. If you have questions regarding the construction schedule or the work being done, please contact the contractor's public representative.

Contractors are required to provide two business day's notice to a homeowner/business if the homeowner/business owner's property will be directly impacted by the work. This includes access issues.

Construction Zone Details

  • Planned Detours: Yes - to be determined
  • Planned Lane Restrictions: Yes - as needed throughout project
  • Planned Road Closures: Yes - North TJ Meenach Drive from TJ Meenach Bridge to Northwest Boulevard will be closed the duration of the project; Downriver Boat Launch area will be closed the duration of the project
  • Planned Utility Work: Yes – stormwater and sewer improvements as needed
  • Pavement Cut Moratorium In Effect: Yes

Note: the contractor will do its best to minimize impacts on the public, but unforeseen circumstances may result in the need to temporarily revise traffic restrictions. For everyone's safety, please obey all traffic signs.

Expected Construction Start Date: Summer 2022

Expected Construction Completed Date: Fall 2022

Contract Award Date: Expected to be bid in April of 2022

Contractor: To be determined

City Project Manager - Construction Phase: John Hogberg, 509.625.7722, jhogberg@spokanecity.org

City Project Manager - Design Phase: Jonathan Adams, 509.625.6700, jradams@spokanecity.org


Contact Information

For questions or concerns regarding the construction work or the construction schedule, please contact the contractor's public representative:
To be determined

If the contractor's public representative cannot resolve your issue, please contact the City of Spokane - Engineering Services at 509.625.6700 or eraea@spokanecity.org.