Project Number: 2014153
Status: Completed
Construction Estimate: $3,575,095
Project Description: This project will design and construct stormwater and sanitary sewer improvements in coordination with the TJ Meenach Drive street reconstruction project.
Project Location(s)
North TJ Meenach Drive from TJ Meenach Bridge to Northwest Boulevard, including Downriver Boat Launch area
Construction Start Date: March 2023
Expected Construction Completed Date: October 2023
Contract Award Date: January 2023
Contractor: Halme Construction
City Project Manager - Construction Phase: John Hogberg, 509.625.7722, jhogberg@spokanecity.org
City Project Manager - Design Phase: Jonathan Adams, 509.625.6700, jradams@spokanecity.org